Time Line/Governor's Parkway Project

 
December 11, 2007 Letting Date
  Tree Clearing Contract Troy Road to Ridgeview Road
  Stipulate Completion Date April 1, 2008
  Est. Cost of Contract $220,000
 
January 8 or February 12, 2008 Letting Date
  Governor's Parkway Mainline Construction/Troy Road to IL Rt 143
  Stipulate Completion Date September 2008 from Troy Road to District Drive
  Includes 1000± feet of District Drive
  Est. Cost of Contract $12,300,000
  Construction Engineering $1,200,000
 
Fall 2008 (August?) Letting Date
  Ridgeview Road/IL Rt 143 to Goshen Road
  Est. Cost of Contract $2,500,000
  Construction Engineering $250,000
 
    Total Cost $16,470,000
 
District Drive High School Contract $325,000
 
    Total $16,795,000
 
Does not include incentive cost for completion dates
      ±200,000
 
    Total Estimate Cost $17,000,000
 
Anticipated Funding Program
  FY08 $14,000,000  
  FY09 $3,000,000  
 
 
 
 
 